International Standards and Conformity Assessment for all electrical, electronic and related technologies

TC 91

Electronics assembly technology

 

Approval

P-Members

Voting
P-Members

Approving
Approval %
Criteria
Result
9 9 100 >=66.7% APPROVED

Participation

Number of

P-Members
P-Members

approving and

participating
Criteria
Result
11 6 >=4 (if <=16)
>=5 (if >=17)
APPROVED

 Illustration: Voting

Voting Result

APPROVED

Document 91/1590/NP

 

Project : PNW 91-1590

PNW 91-1590: MATERIALS FOR PRINTED BOARDS AND OTHER INTERCONNECTING STRUCTURES – Part 6-11: Sectional specification set for reinforcement materials – Specification for finished fabric woven from “Low Dk” glass for printed boards

 

Reference Circulation date Closing date Downloads
91/1590/NP 2019-07-12 2019-10-04
Compilation of Comments
CC file    
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Austria O 2019-10-03 A N -
Belgium O 2019-10-04 A N -
Brazil O 2019-10-04 A N -
Bulgaria O -
China P 2019-09-23 Y Y Y Y
Czech Republic O -
Denmark O -
Finland P 2019-09-24 Y Y Y -
France O 2019-10-03 A N -
Germany P 2019-09-26 Y Y Y Y
Greece - 2019-10-03 Y Y N -
Hungary O -
India P 2019-10-01 A N -
Israel O -
Italy P 2019-10-02 Y Y N -
Japan P 2019-09-26 Y Y Y -
Korea, Republic of P 2019-10-04 Y Y N -
Netherlands P 2019-09-27 A N -
Norway O -
Poland O -
Portugal O 2019-10-04 A N -
Qatar - 2019-10-02 A N -
Romania O 2019-10-04 A N -
Russian Federation P 2019-10-03 Y Y N -
Serbia O -
Slovenia O -
Spain O -
Sweden O -
Switzerland O -
Turkey O -
Ukraine O -
United Kingdom P 2019-09-12 Y Y Y -
United States of America P 2019-10-04 Y Y Y Y

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: (0)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a 2/3 majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.