International Standards and Conformity Assessment for all electrical, electronic and related technologies

SC 48B

Electrical connectors

 

Approval

P-Members

Voting
P-Members

Approving
Approval %
Criteria
Result
18 18 100 >50% APPROVED

Participation

Number of

P-Members
P-Members

approving and

participating
Criteria
Result
22 8 >=4 (if <=16)
>=5 (if >=17)
APPROVED

 Illustration: Voting

Voting Result

APPROVED

Document 48B/2290/NP

 

Project : IEC 61076-2-111 Ed. 1.0

IEC 6XXXXX-2-1XX Ed 1.0: Connectors for electronic equipment - Product requirements - Part 2-1XX: Circular connectors - Detail specification for power connectors M12 with screw-locking

 

Reference Circulation date Closing date Downloads
48B/2290/NP 2012-03-02 2012-06-08
Compilation of Comments
CC file    
Voting Result
48B/2307/RVN 2012-06-15  
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Austria P 2012-05-22 Y N N N -
Belgium P 2012-05-08 Y N N N -
Brazil P 2012-06-06 Y N N N -
China P 2012-06-08 Y Y N N -
Czech Republic P 2012-05-21 Y Y N N -
Denmark P 2012-06-07 Y Y N Y -
Finland P
France P 2012-05-14 Y Y N Y -
Germany P 2012-05-30 Y N N Y Y
Greece - 2012-06-08 Y N N N -
Hungary P 2012-06-05 A N N N -
Ireland P 2012-05-29 Y Y N N -
Israel P 2012-06-07 A N N N -
Italy P 2012-06-07 Y Y N Y Y
Japan P 2012-06-01 Y Y N Y Y
Korea, Republic of O 2012-05-07 Y N Y N -
Netherlands P 2012-06-06 Y Y N Y -
Pakistan P 2012-06-08 Y N N N -
Portugal - 2012-06-08 A N N N -
Romania P 2012-06-07 Y N N N -
Russian Federation P 2012-06-08 Y N N N -
Spain P 2012-06-07 Y Y N N -
Switzerland P 2012-03-29 A N N N -
United Kingdom P 2012-05-21 Y N N Y Y
United States of America P 2012-06-06 Y N N Y Y

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: Finland(1)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a simple majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.