International Standards and Conformity Assessment for all electrical, electronic and related technologies

TC 114

Marine energy - Wave, tidal and other water current converters

 

Approval

P-Members
Voting
P-Members
Approving
Approval %
Criteria
Result
10 8 80 >50% APPROVED

Participation

Number of
P-Members
P-Members
approving and
participating
Criteria
Result
14 2 >=4 (if <=16)
>=5 (if >=17)
REJECTED

 Illustration: Voting

Voting Result

Document 114/92/NP

 

Project : IEC/TS 62600-103 Ed. 1.0

Guidelines for the early stage development of wave energy converters: Best practices & recommended procedures for the testing of pre-prototype scale devices

 

Reference Circulation date Closing date Downloads
114/92/NP 2012-03-23 2012-06-29
Compilation of Comments
CC file    
Voting Result
114/99/RVN 2012-09-14  
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Belgium - 2012-06-11 A N N N -
Brazil O 2012-06-29 A N N N -
Canada P 2012-06-29 Y N N Y Y
China P 2012-06-29 Y Y N N -
Denmark P 2012-06-25 N Y N Y Y
Finland - 2012-06-25 Y Y N N -
France P 2012-06-26 A N N N -
Germany P 2012-06-26 Y Y N N Y
Greece - 2012-06-29 A N N N -
Ireland P 2012-06-12 Y Y N N -
Japan P 2012-06-28 Y N N N -
Korea, Republic of P 2012-05-16 Y N N N -
Netherlands P 2012-06-28 A N N N -
Norway P
Portugal O 2012-06-29 Y N N N Y
Qatar - 2012-06-27 Y Y N N -
Romania O 2012-06-07 Y N N N -
Russian Federation O 2012-06-26 Y N N N -
Spain P 2012-06-29 Y Y N Y -
Sweden P 2012-06-14 A N N N -
United Kingdom P 2012-06-28 Y Y N N -
United States of America P 2012-06-20 N N N N Y

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: Norway(1)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a simple majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.