International Standards and Conformity Assessment for all electrical, electronic and related technologies

TC 100

Audio, video and multimedia systems and equipment

 

Approval

P-Members

Voting
P-Members

Approving
Approval %
Criteria
Result
12 11 91.7 >50% APPROVED

Participation

Number of

P-Members
P-Members

approving and

participating
Criteria
Result
24 2 >=1 (if <=0)
>=2 (if >=1)
APPROVED

 Illustration: Voting

Voting Result

APPROVED

Document 100/1961/NP

 

Projects :
IEC 62827-1 Ed. 1.0
IEC 62827-1 Ed. 1.0
IEC 62827-2 Ed. 1.0
IEC 62827-3 Ed. 1.0

Management Protocol of Wireless Power Transfer for Multi-devices

 

Reference Circulation date Closing date Downloads
100/1961/NP 2012-03-09 2012-06-15
Compilation of Comments
CC file    
Voting Result
100/2025/RVN 2012-08-10  
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Australia P
Austria P 2012-06-14 A N N N -
Belarus O 2012-06-15 Y N N N -
Belgium P 2012-05-21 N N N N Y
China P 2012-06-15 A N N N -
Denmark P 2012-06-12 A Y N N -
Finland P 2012-06-15 A N N N -
France P 2012-04-27 A N N N -
Germany P 2012-06-14 Y N N N -
Greece O 2012-06-12 A Y N N -
India P 2012-05-18 Y N N N -
Ireland P 2012-05-30 Y Y N N -
Israel P 2012-06-14 A N N N -
Italy P 2012-06-15 Y N Y N -
Japan P 2012-06-14 Y N N N -
Korea, Republic of P 2012-06-15 Y Y N Y -
Mexico P 2012-06-14 A N N N -
Netherlands P 2012-06-07 A N N N -
Norway P
Pakistan P 2012-06-15 Y N N N -
Portugal O 2012-06-15 Y Y N N Y
Qatar - 2012-06-14 Y Y N N -
Romania P 2012-06-14 Y N N N -
Russian Federation P 2012-05-24 A N N N -
Slovenia O 2012-03-22 Y N N N -
Spain O 2012-06-14 A N N N -
Turkey P 2012-06-06 A N N N -
Ukraine P 2012-06-05 Y N N N -
United Kingdom P 2012-04-02 Y N N Y -
United States of America P 2012-06-15 Y N N N Y

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: Australia; Norway(2)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a simple majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal

    • for TC 100, in case of more than two thirds of the P-members voting is in favour the acceptance criterion related to the minimum number of nominated technical experts is replaced by: In addition to the Project Leader, there should be nominated at least one expert from a different P-member country.




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.