International Standards and Conformity Assessment for all electrical, electronic and related technologies

TC 26

Electric welding

 

Approval

P-Members

Voting
P-Members

Approving
Approval %
Criteria
Result
12 12 100 >50% APPROVED

Participation

Number of

P-Members
P-Members

approving and

participating
Criteria
Result
16 5 >=4 (if <=16)
>=5 (if >=17)
APPROVED

 Illustration: Voting

Voting Result

APPROVED

Document 26/469/NP

 

Project : IEC 62822-2 Ed. 1.0

PNW 26-469: Basic standard for evaluation methods for equipment for arc welding and allied processes related to human exposure restrictions for electromagnetic fields

 

Reference Circulation date Closing date Downloads
26/469/NP 2011-11-25 2012-03-02
Compilation of Comments
CC file    
Voting Result
26/491/RVN 2012-08-03  
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Austria P 2012-01-19 Y N N Y Y
Belgium O 2012-02-06 A N N N -
China P 2012-03-02 Y Y N Y -
Denmark P 2012-02-21 A N N N -
Egypt P
Finland P 2012-03-01 Y Y N N -
France P 2012-02-29 A N N N -
Germany P 2012-03-01 Y N Y N -
Greece O 2012-02-01 A N N N -
Iran P 2012-02-26 Y N N N -
Italy P 2012-03-02 Y Y N N -
Japan P 2012-02-27 Y N N Y -
Korea, Republic of O 2012-01-23 Y N Y N
Portugal - 2012-03-02 A N N N -
Qatar - 2012-02-28 Y N N N -
Romania P 2012-02-14 Y N Y N -
Russian Federation P 2012-02-22 Y N N N -
Spain O 2012-02-28 Y Y N N -
Sweden P 2012-02-09 Y N N Y -
Ukraine P 2012-02-28 Y Y N N -
United Kingdom P 2012-02-22 A N N N -
United States of America P 2012-03-02 Y N N Y -

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: Egypt(1)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a simple majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.