International Standards and Conformity Assessment for all electrical, electronic and related technologies

TC 25

Quantities and units

 

Approval

P-Members
Voting
P-Members
Approving
Approval %
Criteria
Result
12 11 91.7 >50% APPROVED

Participation

Number of
P-Members
P-Members
approving and
participating
Criteria
Result
17 6 >=4 (if <=16)
>=5 (if >=17)
APPROVED

 Illustration: Voting

Voting Result

APPROVED

Document 25/470/NP

 

Project : IEC 80003-4 Ed. 1.0

IEC 80003 - QUANTITIES FOR E-HEALTH Part 4: Biology

 

Reference Circulation date Closing date Downloads
25/470/NP 2013-07-12 2013-10-18
Compilation of Comments
CC file    
Voting Result
25/478A/RVN 2014-01-10  
 
export to xls file

Result of Voting

Country
Status
Received
Approving
CD
CDV
Participation
Comments
Austria P 2013-10-17 A N N N -
Belgium O 2013-09-24 A N N N -
China P 2013-10-17 A N N N -
Czech Republic P 2013-10-14 Y N Y Y -
Finland O 2013-10-18 Y Y N N -
France P 2013-10-17 Y Y N Y Y
Germany P 2013-10-08 N N N N Y
Greece - 2013-10-14 A N N N -
Ireland - 2013-10-15 Y N N N -
Italy P 2013-10-15 Y N N N Y
Japan P 2013-10-17 Y Y N Y Y
Korea, Republic of P 2013-10-10 Y N N N -
Poland P 2013-10-16 Y N N N -
Portugal - 2013-10-18 A N N N -
Romania P 2013-10-17 Y N N N -
Russian Federation P 2013-10-18 Y N N N -
Serbia P 2013-10-17 A N Y N -
Spain P 2013-10-18 Y Y N Y -
Sweden P 2013-10-14 Y N N Y Y
Switzerland P 2013-10-17 Y N N Y -
United Kingdom P 2013-10-14 A N N N -
United States of America P 2013-10-18 A N N N -

NOTES:


The final result of voting will be indicated in the Report of Voting (RVN), as P-members have the possibility to nominate an expert one month after the closing date -- complete information in AC/172/2000



  1. Approving: Does the National Committee approve the addition of the new proposal to the program of work of the committee [Yes/No] ?

  2. Only votes received from P-members before the closing date are counted in determining the decision.

  3. P-members not voting: (0)

  4. CD/CDV: Does the National Committee agree with direct submission of the draft accompanying the proposal as a Committee Draft/Committee Draft for Voting [Y if Yes] ?

  5. Participation : Is the National Committee prepared to participate in the development of the project [Yes/No] ? (Only those voting in favour of the proposal itself have their willingness to participate considered as part of the final decision.)

  6. Acceptance criteria for TS/IS:

    • approval of the work item by a simple majority of the P-members voting

    • at least 4 P-members in the case of a committee with 16 or fewer P-members, or at least 5 P-members in the case of committees with 17 or more P-members, have nominated or confirmed the name of an expert and approved the new work item proposal




*Comments rejected because they were not submitted in the IEC Comment form.
**Vote rejected due to lack of justification statement.