Committee | Working Groups | Project Leader | Current Status | Frcst Pub Date | Stability Date |
|---|---|---|---|---|---|
| SC 65C | JWG10 | F. Russo | RDIS | 2013-05 | 2018 |
History
Stage | Document | Downloads | Decision Date | Target Date | ||||
|---|---|---|---|---|---|---|---|---|
| PNW |
| 2010-04-16 | ||||||
| ANW |
| 2010-07-23 | 2010-08-31 | |||||
| 1CD |
| 2011-01-14 | 2011-03-31 | |||||
| A2CD |
| 2011-08-26 | 2011-10-15 | |||||
| CCDV |
| 2011-12-16 | 2011-12-16 | |||||
| ADIS |
| 2012-06-01 | 2012-08-31 | |||||
| DEC | 2012-11-05 | 2012-12-31 | ||||||
| RDIS | 2013-02-08 | 2012-11-30 | ||||||
| CDIS | 2013-02-15 | |||||||
| APUB | 2013-04-15 | |||||||
| BPUB | 2013-04-30 | |||||||
| PPUB | 2013-05-31 | |||||||
Project
IEC 61784-5-x Ed. 1.0
Industrial communication networks - Profiles - Part 5-n Installation of fieldbuses - Installation profiles for CPF n
Remark:
- (For this NP: n = 8, 13, 16, 17 and 18) - Project plan: CDV 2011-11 FDIS 2012-06 - Also of interest to TC 57. - Relevant documents to be considered: IEC 61918, IEC 61158 series, IEC 61784-1 and IEC 61784-2 - Relationship of project to activities of other international bodies: IEC SC17B, SC22G, TC57 and ISO 184 SC5 - At the final stage this project will be splited on Part 5-1, 5-8, 5-13, 5-16, 5-17, 5-18 - Liaison organizations: Foundation Fieldbus, CC-LINK Partner Association, Safety Network International, SERCOS - Coordination within ISO or IEC SC65C/MT9