Committee | Working Groups | Project Leader | Current Status | Frcst Pub Date | Stability Date |
|---|---|---|---|---|---|
| TC 81 | 11 | D. Kokkinos | PPUB | 2012-03 | 2017 |
History
Stage | Document | Downloads | Decision Date | Target Date | ||||
|---|---|---|---|---|---|---|---|---|
| PNW |
| 2007-06-15 | ||||||
| ANW |
| 2007-11-23 | 2007-10-31 | |||||
| 1CD |
| 2007-11-23 | 2008-01-31 | |||||
| CDM |
| 2008-05-30 | 2008-03-31 | |||||
| A2CD | 2009-04-03 | 2009-05-15 | ||||||
| 2CD |
| 2009-09-18 | 2010-02-28 | |||||
| ACDV |
| 2010-01-08 | 2010-01-31 | |||||
| CCDV |
| 2010-12-03 | 2010-12-31 | |||||
| ADIS |
| 2011-06-24 | 2011-08-15 | |||||
| DEC | 2011-09-21 | 2011-09-30 | ||||||
| RDIS | 2011-09-29 | 2011-10-15 | ||||||
| CDIS |
| 2011-11-25 | 2011-12-31 | |||||
| APUB |
| 2012-01-31 | 2012-01-31 | |||||
| BPUB | 2012-02-01 | 2012-02-15 | ||||||
| PPUB | 2012-02-10 | 2012-03-15 | ||||||
Project
IEC 62561-1 Ed. 1.0
Lightning protection system components (LPSC) - Part 1: Requirements for connection components
Remark:
- SMB/4270/DL approved for CCDV: 2010-12 - A2CD: Decision taken at TC81 meeting 2009-04, observations on NC comments given in CC document circulated in 2008 were not changed. - Origin CENELEC - Project plan: CDV 2008-12, FDIS 2009-10 - the project relates directly to the activities of CENELEC TC81X - Relevant docs to be considered: IEC 62305-1, IEC 62305-3, EN 50164-1 and A1 - Targets: CD 2009-06, IS 2010-12
Associated Documents:
81/315/INF